Kumaraswamy writes to Karnataka CM over 10-month delay in land allocation for Mandya industrial projects

Bengaluru, Oct 22 (IANS) Union Minister for Heavy Industries and Steel, H.D. Kumaraswamy, has written to Karnataka Chief Minister D.K. Shivakumar, expressing concern over delay in allocating land for two proposed testing facilities in Mandya district: A Construction and Infrastructure Equipment (CIE) Testing Centre and an Electric Vehicle (EV) Testing Centre.

It can be noted that Union Minister Kumaraswamy represents Mandya Lok Sabha seat.

The two facilities, proposed by the Automotive Research Association of India (ARAI), are expected to strengthen India’s automotive and electric mobility ecosystem, promote technological development and create industrial and employment opportunities in the region.

In his letter to the Chief Minister, Union Minister Kumaraswamy, detailed the series of meetings, official communications between the state and central governments, meeting minutes and other documents relating to the proposed projects. He subsequently released these records to highlight what he described as an unacceptable delay in the allocation of land.

The Union Minister also attached newspaper reports containing the Chief Minister’s own statements regarding the proposed ARAI facility in Mandya.

The letter was delivered to Chief Minister’s Additional Chief Secretary Tushar Girinath at Vidhana Soudha by Kumaraswamy’s representatives. Following its submission, the Union Minister also spoke with Tushar Girinath about the matter.

In his letter, Kumaraswamy drew the Chief Minister’s attention to the nearly 10-month delay in allocating land for the two facilities proposed by ARAI, a leading automotive research and development institution operating under the Union Ministry of Heavy Industries.

He noted that despite repeated consultations, site inspections, technical assessments and meetings with the relevant departments, the Mandya district administration and the Karnataka Industrial Area Development Board (KIADB) had yet to finalise the land allocation.

Kumaraswamy outlined the steps taken by ARAI and the authorities to identify suitable land for the proposed facilities.

On March 16, 2026, an ARAI team visited sites at Basaralu, the Mandya Sugar Factory and the K.R. Pet industrial area in Mandya district. The team subsequently held detailed discussions with the Deputy Commissioner of Mandya regarding land availability.

A meeting was also held on March 17 at Vikas Soudha with the Principal Secretary of the Department of Commerce and Industries.

On March 20, ARAI submitted detailed information on the technical requirements for the proposed facilities to the district administration.

Kumaraswamy further recalled meeting Karnataka Industries Minister, M.B. Patil, at Vidhana Soudha on April 13, 2026, to discuss the project’s scope and land requirements.

On May 6, the Mandya district administration provided ARAI with details of sites identified at Basaralu and Heggedahalli for technical evaluation.

An ARAI technical team subsequently inspected the identified locations, including a site at Yelechakanahalli village, on May 18.

A review meeting was held on September 16, 2026, at Vikas Soudha under the chairmanship of the Principal Secretary of the Department of Commerce and Industries, with representatives from ARAI, the Mandya district administration and KIADB in attendance. During the meeting, the suitability of sites at Basaralu and Yelechakanahalli was examined in detail.

According to Kumaraswamy’s letter, approximately 100 acres at Basaralu was considered potentially suitable for the CIE Testing Centre, subject to improvements in road connectivity. An additional 60 acres would be required for the EV Testing Centre.

Yelechakanahalli was also examined as an alternative location where both facilities could potentially be established together, with provision for a long testing track and an adjoining industrial hub.

However, the alternative site presented challenges, including the acquisition of private land and the need to improve connectivity to the Mysuru–Bengaluru Highway and construct a railway overbridge.

Following the review, ARAI wrote to the Principal Secretary and the Mandya Deputy Commissioner on September 17, seeking land allocation at Yelechakanahalli and Basaralu, respectively.

The meeting minutes became available on September 25. On September 28, ARAI submitted a revised proposal to the district administration, requesting approximately 100 acres at Basaralu for the CIE facility and an additional 60 acres for the EV Testing Centre, preferably adjoining the first parcel.

Kumaraswamy described the revised proposal as a practical approach that would allow work on the CIE facility to proceed while the additional land required for the EV Testing Centre was addressed.

Despite these efforts and the identification of a workable option, the land allocation remains pending, he said.

Concluding his letter, Kumaraswamy appealed to Shivakumar to intervene personally and ensure that the land required for the ARAI facilities was allocated at the earliest.

He stressed that the projects could strengthen Mandya’s industrial ecosystem, attract technology-driven investment and create valuable employment opportunities for young people in Karnataka.

“Keeping in view all the above factors, I once again request you, through this letter, to immediately allocate the land required for the ARAI centre in Mandya district. This is essential for the development of the industrial sector and for creating employment opportunities for our youth. Rather than limiting ourselves to assurances in newspapers and the media, we must ensure that the necessary action is taken,” Kumaraswamy stated.

The Union Minister released the relevant correspondence, meeting records and supporting documents to the media, maintaining that the record of discussions between the concerned authorities demonstrated the need for an early decision on land allocation.

–IANS

mka/rad